2022-10-02 11:18

10Month1In the morning, Deputy General Manager Yang Yumin, Deputy General Manager Dong Jinghua, Assistant General Manager and General Manager of the Technical Center Li Huafeng, General Manager of the Procurement Center Zhang Kuiqi, Dean of the Construction Engineering Institute Wang Yige, and Director of the Party Committee Office Wu Haifeng went to the project site of the New Energy Intelligent Network Innovation Experimental Base of China FAW R&D Institute, the Audi FAW New Energy Vehicle Factory Project, and the BYD New Energy Power Battery Phase I Project to deliver holiday greetings to employees on site and sing 'My Motherland and I' together with everyone, allowing everyone to truly feel the company's care and the festive atmosphere./The New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute
Currently, the first and second phases of the New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute have entered the public utility and decoration stage; the third phase has entered the masonry plastering and public utility decoration construction stage; the main structure of the fourth phase has been completed, with masonry, plastering, and external maintenance construction ongoing, and decoration phase has entered; construction of roads and external networks is progressing in sections. Each phase has customized a plan for intensive work over a hundred days to ensure milestones and timelines.Audi FAW New Energy Vehicle Factory ProjectCurrently, the first and second phases of the New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute have entered the public utility and decoration stage; the third phase has entered the masonry plastering and public utility decoration construction stage; the main structure of the fourth phase has been completed, with masonry, plastering, and external maintenance construction ongoing, and decoration phase has entered; construction of roads and external networks is progressing in sections. Each phase has customized a plan for intensive work over a hundred days to ensure milestones and timelines.
The temporary roads and enclosures within the Audi FAW New Energy Vehicle Factory Project have all been completed; the main internal pipeline network has been basically completed; the foundation construction for each workshop in the factory area has been completed.
Currently, the first and second phases of the New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute have entered the public utility and decoration stage; the third phase has entered the masonry plastering and public utility decoration construction stage; the main structure of the fourth phase has been completed, with masonry, plastering, and external maintenance construction ongoing, and decoration phase has entered; construction of roads and external networks is progressing in sections. Each phase has customized a plan for intensive work over a hundred days to ensure milestones and timelines.99%Currently, the first and second phases of the New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute have entered the public utility and decoration stage; the third phase has entered the masonry plastering and public utility decoration construction stage; the main structure of the fourth phase has been completed, with masonry, plastering, and external maintenance construction ongoing, and decoration phase has entered; construction of roads and external networks is progressing in sections. Each phase has customized a plan for intensive work over a hundred days to ensure milestones and timelines.
; steel structure construction has been completed85%, assembly and hoisting of the grid frame have been basically completed, and installation of external protective structures is currently underway to ensure that the project meets its goal of warm closure by the end of the year.BYD New Energy Power Battery Phase I ProjectThe design of BYD's New Energy Power Battery Phase I Project has been fully completed, and the general contractor for civil engineering has completed bidding procurement for construction. The project foundation is completed
Currently, the first and second phases of the New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute have entered the public utility and decoration stage; the third phase has entered the masonry plastering and public utility decoration construction stage; the main structure of the fourth phase has been completed, with masonry, plastering, and external maintenance construction ongoing, and decoration phase has entered; construction of roads and external networks is progressing in sections. Each phase has customized a plan for intensive work over a hundred days to ensure milestones and timelines.80%Currently, the first and second phases of the New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute have entered the public utility and decoration stage; the third phase has entered the masonry plastering and public utility decoration construction stage; the main structure of the fourth phase has been completed, with masonry, plastering, and external maintenance construction ongoing, and decoration phase has entered; construction of roads and external networks is progressing in sections. Each phase has customized a plan for intensive work over a hundred days to ensure milestones and timelines.
, and steel structure main construction has begun.In the morning, Deputy General Manager Mu Xuefeng, Deputy General Manager Li Yunsheng, Assistant General Manager and General Manager of Business Center Shi Fu, Dean of Manufacturing Technology Institute Lu Zhendong, Executive Deputy General Manager of Equipment Division and General Manager of Landi Company Song Wei, and Minister of Production Management Department Yang Xueyong visited the Ulsan factory equipment capability enhancement project and Ulsan factory water-based paint renovation project site to deliver greetings to employees working on the front line and provide valuable suggestions on safety, progress, quality, etc.Ulsan Factory Equipment Capability Enhancement Project
In the Ulsan Factory Equipment Capability Enhancement Project, sections such as painting, final assembly, and digitalization have been implemented ahead of schedule for part of the renovation content. Currently, production lines such as expanded factory buildings and testing lines in Final Assembly Workshop No. 2 have successfully switched production and are in use.Ulsan Factory Water-Based Paint Renovation ProjectThe first vehicle rolled off the production line on that day.Ulsan Factory Water-Based Paint Renovation ProjectIn the Ulsan Factory Equipment Capability Enhancement Project, sections such as painting, final assembly, and digitalization have been implemented ahead of schedule for part of the renovation content. Currently, production lines such as expanded factory buildings and testing lines in Final Assembly Workshop No. 2 have successfully switched production and are in use.
10Month1日上午,公司副总经理穆学峰、副总经理李允升、总经理助理兼商务中心总经理史复、制造技术院院长陆振东、装备事业部常务副总经理兼蓝迪公司总经理宋伟、商务中心生产管理部部长杨学勇来到蔚山工厂装备能力提升项目、蔚山工厂涂二水性漆改造项目现场,对奋斗在一线的员工送去慰问,并对项目的安全、进度、质量等方面提出宝贵意见。
Currently, the first and second phases of the New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute have entered the public utility and decoration stage; the third phase has entered the masonry plastering and public utility decoration construction stage; the main structure of the fourth phase has been completed, with masonry, plastering, and external maintenance construction ongoing, and decoration phase has entered; construction of roads and external networks is progressing in sections. Each phase has customized a plan for intensive work over a hundred days to ensure milestones and timelines.蔚山工厂装备能力提升项目 Currently, the first and second phases of the New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute have entered the public utility and decoration stage; the third phase has entered the masonry plastering and public utility decoration construction stage; the main structure of the fourth phase has been completed, with masonry, plastering, and external maintenance construction ongoing, and decoration phase has entered; construction of roads and external networks is progressing in sections. Each phase has customized a plan for intensive work over a hundred days to ensure milestones and timelines.
蔚山工厂装备能力提升项目,涂装、总装、数字化等板块较原计划提前实施改建区部分改造内容。目前,总装二车间扩建区厂房及检测线等生产线已成功切换转产、投入使用。
Currently, the first and second phases of the New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute have entered the public utility and decoration stage; the third phase has entered the masonry plastering and public utility decoration construction stage; the main structure of the fourth phase has been completed, with masonry, plastering, and external maintenance construction ongoing, and decoration phase has entered; construction of roads and external networks is progressing in sections. Each phase has customized a plan for intensive work over a hundred days to ensure milestones and timelines.蔚山工厂涂二水性漆改造项目 Currently, the first and second phases of the New Energy Intelligent Network Innovation Experimental Base Project of China FAW R&D Institute have entered the public utility and decoration stage; the third phase has entered the masonry plastering and public utility decoration construction stage; the main structure of the fourth phase has been completed, with masonry, plastering, and external maintenance construction ongoing, and decoration phase has entered; construction of roads and external networks is progressing in sections. Each phase has customized a plan for intensive work over a hundred days to ensure milestones and timelines.
蔚山工厂涂二水性漆改造项目9Month15日首车下线,30日NAT车型SOP, completing all required milestones from the owner side. Next, debugging work for other vehicle models will begin.