Let ideals soar and dreams come true. On November 10, 2021, at 11:10 AM, the SOP of the E-QM5 model and the ceremony for the first complete vehicle off the production line were grandly held in the final inspection chain of the assembly workshop. Zhang Shuo, the factory director of FAW Group's Prosperity Factory, Deputy Factory Director Zhang Jijun, Engineering Logistics Department Assembly Director Dong Wei, and Senior Director Liu Donglin attended the ceremony.Long hairGeneral Manager of New Energy Shi Liwei, Deputy Dean of Manufacturing Technology Institute of the Ninth Academy Lu Zhendong and other leaders attended the ceremony. Representatives from the Prosperity Factory workshop, project team representatives from the Engineering Logistics Department, management team from the Ninth Academy, and subcontractor representatives witnessed this exciting moment together.

Major milestone nodes of Hongqi Prosperity Factory:
On April 15, 2020, the project groundbreaking started;
On July 1, 2020, the main construction commenced;
On December 30, 2020, the factory was warm and sealed;
On March 1, 2021, process equipment entered the factory;
On June 29, 2021, the factory was completed;
On November 10, 2021, the first E-QM5 complete vehicle rolled off the line.
The rolling off of the first E-QM5 complete vehicle marks the official start of mass production at Prosperity Factory. As the first vehicle slowly drove off the assembly line, a technologically advanced digitalized, intelligent, flexible, and green automotive industry benchmark factory officially joined FAW's manufacturing landscape, which will surely help achieve Hongqi's '14th Five-Year' strategic goals.
After countless trials and tribulations, only to be tempered into steel. For this moment to arrive, members of the Ninth Academy project team have silently dedicated their hard work and tenaciously overcome various difficulties. With joy in harvest and reaching new heights, the team will continue to promote unity and cooperation and tackle challenges head-on to accomplish even more daunting tasks of optimizing rhythm and enhancing production capacity!
Related News
Contact Information
Customer service telephone:+86 431 85125000
E-mail:marketing@cjxjy.com
Address: 1958 Chuangye Street, Changchun, China